About the EIA Directive (2011/92/EU)
The Environmental Impact Assessment Directive 2011/92/EU requires certain public and private projects likely to have significant effects on the environment to undergo an environmental impact assessment before development consent is granted.
The Directive aims to secure a high level of environmental protection by ensuring that the likely significant effects of projects on factors such as population, biodiversity, soil, water, air, climate, material assets, cultural heritage and the landscape are identified, described and assessed in advance. It applies to a wide range of projects listed in its Annexes, including major infrastructure such as roads, airports and waste installations, and integrates environmental considerations into authorisation decisions. Member States are required to transpose the Directive into national law, designate competent authorities to carry out EIA procedures, and ensure effective public participation and access to justice in environmental matters. Compliance is enforced through national courts and administrative bodies, as well as EU-level oversight and, where necessary, infringement proceedings before the Court of Justice of the European Union.
Friends of Killymooney Lough v. an Coimisiún Pleanála and Others [2025] IEHC 407
The applicants sought a certiorari quashing the order of the first respondent, an Bord Pleanála (“the Board”), for the construction of a single storey retail unit, 297 car parking spaces, a drive through ‘café’, a petrol filling station and associated development at Cock Hill, Cavan Town, Co.Cavan. The applicant also sought an additional certiorari quashing the decision by the Minister for the Environment, Climate and Communications because he made a legal error by failing to conduct a mandatory environmental assessment at the correct time as required by the Climate Action Plan, thus making the entire decision invalid.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU):
The applicant argued that the Board failed to identify the effect of the traffic increase that the Developer EIA acknowledged the Proposed Development would cause, which could potentially increase emissions, thereby failing to adhere to legal obligations to reduce emissions.
The Court rejected this argument. It found that, contrary to the applicant's claim, the Board did have regard to climate goals. This was demonstrated through the Inspector's report, which engaged with both local and national climate policy, and by affidavit evidence from a Board member confirming awareness of the relevant Climate Action Plan. The Court held that the Inspector's conclusion, that the quantified increase in emissions was minimal and thus not a "significant effect", was an evaluative judgement the Board was entitled to make on the evidence before it. The applicant failed to demonstrate that this judgement was incorrect.
Key Points of EU Law
The Court emphasised that the concept of a “significant effect” under the EIA Directive does not establish a precise legal test. Whether a project is likely to have a significant effect is a question of degree that calls for the exercise of judgement by the expert planning authority. This evaluative judgement is reviewable by the courts only on the grounds of irrationality or unreasonableness, not on the merits.
The High Court firmly rejected the applicant's argument that the EIA was defective for failing to assess the cumulative impacts of all vehicle emissions from all projects nationally. It held in para. 197 that such an interpretation would impose an "impossibly onerous and unworkable obligation" on developers and authorities, which is not required by the text, context, or purpose of the EIA Directive.
Conclusion
The High Court dismissed the applicant's judicial review challenge in its entirety. The Court found no legal basis to quash the planning permission for the retail development, holding that the planning authority had properly considered climate policies and carried out a valid environmental impact assessment. It also rejected the separate challenge to the national 2024 Climate Action Plan, deeming it an impermissibly abstract and academic challenge.
Link to Judgment ↑ Return to Table of Contents
Ventaway Ltd v. an Comisiúin Pleanála [2025] IEHC 406
The applicant sought judicial review after the respondent refused planning permission for a 24-storey mixed-use building in Dublin. One of the key grounds for challenge was that the respondent failed to carry out its own EIA. The applicant argued this was a breach of national law and Articles 3-9 of the EIA Directive, which outline the core procedures for an EIA. The Court noted that the respondent’s decision contained no record of such an assessment, despite the project being accompanied by an Environmental Impact Assessment Report.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU): Humphreys J. explicitly declined to make a definitive ruling on whether the EIA Directive itself mandates an assessment prior to a refusal of permission, because the High Court had determined that the issue focused on the unambiguous requirements of the Planning and Development Act 2000. This was despite the respondent's argument that the Directive's obligation under Article 2(1) to carry out an EIA “…before development consent is given” did not arise upon a refusal for "non-EIA reasons," a requirement it deemed unjustifiable and burdensome. Since the case could be, and was, resolved on this straightforward reading of national law, which the Court found to be clear and mandatory, there was no legal necessity to interpret the underlying EU Directive, rendering the complex EU law point moot.
Key Points in EU Law
The Court noted that the analysis of the EIA Directive was obiter, stating that only if the national law were ambiguous would a question for a preliminary reference to the CJEU arise.
Conclusion
The High Court granted the applicant's request for an order of certiorari, quashing the respondent's decision to refuse permission. The Court found the decision invalid
McGowan v. An Coimisiún Pleanála [2025] IEHC 405
The applicants sought a certiorari quashing the decision of the respondent, to grant planning permission for a proposed windfarm development including 13 wind turbines in Bunnyconnellan, Co. Mayo and a hydrogen plant in Castleconnor, Co. Sligo. The applicant argued that the impugned decision of the respondent was invalid as it violated Articles 2, 3, 5, 8, 8a and Annex IV of the EIA Directive (Directive 2011/92/EU) as the respondent failed to carry out a lawful EIA to adequately assess the environmental effects of the continuation of domestic turf cutting at the site for the duration of the initial permission, and that the respondent failed to assess the baseline.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU):
The Court engaged significantly with the Directive's provisions, particularly its definition of “development consent” as utilised in Article 2(1) of the EIA Directive. ‘Development consent’ as defined in Article 1(2)(c) of the Directive recognises that authorisation for a project may involve 'the decision of the competent authority or authorities'. This wording was used in rejecting the applicants' argument for a mandatory joint assessment procedure, confirming that the EU legal framework does not require the centralisation of EIA functions within a single body.
Furthermore, the Court's analysis affirmed that the Directive’s requirements are to be interpreted in a practical manner, focusing on whether the assessment, as a whole, adequately identified, described, and assessed the project's likely significant effects on the environment, including in-combination effects with other projects, without imposing obligations that extend to activities beyond the developer's control.
Key Points in EU Law
The High Court rejected the argument that the EIA requires a single, joint assessment to be conducted by multiple consenting authorities. As defined by Article 1(2)(c) of the Directive expressly states that multiple authorities may be involved, and there is no EU law obligation to centralise all EIA functions in one decision-maker.
The Court endorsed a substantive rather than a formalistic approach to reviewing the EIA. It reiterated that a challenge to the adequacy of an EIA must be supported by evidence, typically expert evidence, to demonstrate a legal flaw. Mere assertion or a merits-based disagreement dressed in legal language is insufficient to vitiate a decision.
Conclusion
The High Court dismissed the proceedings. It found that the applicants had failed to plead their case with sufficient particularity, provide evidence to discharge the burden of proof, and establish that the respondent's decision was made in breach of the EIA Directive. The Court upheld the planning permission, confirming that the EIA carried out was lawful under EU law.
Concerned Residents of Coolkill Sandyford Downs and Lamb's Brook and Another v. An Bord Pleanála [2025] IEHC 265
The applicants sought certiorari quashing the order of the respondent, an Bord Pleanála (“the Board”), which granted planning permission to the notice party for a strategic housing development. They argued the decision was invalid because it violated the density rules in the County Development Plan 2022-2028 (“CDP”) and misapplied the Sustainable Urban Housing Guidelines. The applicants alleged non-compliance with other CDP standards. Secondly, the applicant believed that the Board breached multiple EIA provisions under the 2001 Regulations and the EIA Directive, and the EIA Screening Report was non-compliant with Schedule 7A of the Regulations and Annex III of the Directive.
Relevant EU Law
- EIA Directive (Directive 2011/92/EU): The case centred on the legal test for screening under Article 4(2) to (6) of the EIA Directive. The Court analysed the core obligation in Article 2(1), which requires an EIA for projects likely to have significant effects on the environment, in light of recent CJEU jurisprudence. The applicant argued that the Board had failed this standard by screening out EIA without adequate site-specific geological information, despite the potential for significant effects from excavation. The Court dismissed this challenge. It found that while the absence of certain site investigation data was regrettable, the Board had acted with sufficient information. The Board was able to reach a reasonable screening judgement as it possessed additional pertinent data, such as geological mapping and party submissions. The Court emphasised that an EIA screening is intended to identify the relatively small number of projects requiring a full EIA and that a decision can be made on sufficient information even if certain details remain unknown.
Key points in EU Law
The High Court looked to the Waltham Abbey (Case C-41/24) which details the high legal threshold for deciding that an EIA is not required for a project: an EIA is mandatory whenever a project carries a risk of significant environmental effects. This requirement is interpreted through the lens of the precautionary principle, meaning a risk is deemed to exist if objective evidence cannot exclude the likelihood of significant harm. Consequently, to lawfully screen out an EIA, the competent authority must be able to conclude with certainty that all reasonable scientific doubt has been ruled out. This requirement, to base the decision on the “…most comprehensive information possible”, must be applied in a functional and proportionate manner. This standard does not demand an absolute or exhaustive level of information, but rather information that is objectively sufficient for the screening task at hand, considering what may reasonably be required of a developer.
Conclusion
The High Court dismissed the challenge to the EIA screening. Holland J. determined that the respondent had had a sufficient, rational basis for its decision that the project was not likely to have significant environmental effects, despite the absence of certain site-specific data. The ruling thereby affirms that the EIA screening process under the EIA Directive serves to avoid unnecessary full assessments where adequate information exists to lawfully exclude significant effects.
Byrne v. Fingal County Council and Others [2025] IEHC 204
The applicant challenged the exercise of powers by the first respondent pursuant to s. 38 of the Road Traffic Act 1994 (“1994 Act”) and s. 95 of the Road Traffic Act 1961 (“1961 Act”) to make alterations to the traffic management arrangements on a street in Malahide. The applicant sought interlocutory relief in respect of the pedestrianisation of the street.
Relevant EU Directive
- EIA Directive (Directive 2011/92/EU): The applicant sought a declaration that Regulation 120 of the Planning and Development Regulations 2001, as amended, infringed Articles 2(1) and 4(3) of the EIA Directive, and should be set aside or declared invalid. The applicant argued that the respondent's development plan failed to meet the required standard of care, as evidenced by its failure to properly assess the environmental consequences of traffic diversion onto surrounding streets.
Article 2 of the EIA Directive establishes the fundamental rule that an EIA is mandatory for any project likely to have significant environmental effects due to its nature, size, or location. To implement this, Article 4(3) allows member states to create specific definitions for such projects, which Ireland did by establishing a size-based threshold, the 'area involved', for urban development projects in its regulations. In domestic legislation, this ‘area involved’ for urban development is 2 hectares before an EIA is required. The Court rejected the applicant’s argument due to the physical works being restricted to 0.22 hectares and thus considered a “sub-threshold”. Therefore, a mandatory EIA was not required.
The applicant also argued, on the basis of Article 2(1) of the EIA Directive, which states that the Directive's purpose cannot be circumvented by splitting a project the project in question should be considered part of a larger, supra-threshold project. Following CJEU jurisprudence and statements from the Board Inspector’s assessment that the New Street project was "functionally independent" and "not integral" to the other projects. The Court held that it was legitimate for a local authority to advance distinct parts of a wider strategy individually and that no project splitting had occurred on the facts of this case.
Key Points in EU Law
Article 2(1) of the EIA Directive establishes a two-stage test: (i) the "project as a whole" must be identified for assessment, which can extend beyond the specific application for consent; (ii) if a sub-threshold project is part of a larger, supra-threshold project, it may itself require an EIA. Second, the definition of this "whole" is based on factors like geographical proximity, similarity, and functional interdependence. Furthermore, the obligation to consider cumulative effects is not restricted to projects of the same kind.
To determine the "area involved" under Article 4(3) of the EIA Directive, the Court applied the fundamental principle from Kraaijeveld (C-72/95): while member states have discretion to set thresholds, this discretion is limited by the overriding obligation in Article 2(1) to ensure all projects likely to have significant environmental effects are subject to an assessment. It held that the concept of the "area involved" in a project for threshold purposes refers to the physical footprint of the works, not the wider, indirect zone of influence. While an EIA was not warranted, a project that is sub-threshold based on this interpretation must still undergo a screening process to determine if it is likely to have significant environmental effects, ensuring the objective of Article 2(1) is not circumvented.
Conclusion
The High Court largely dismissed the applicant's challenge. While it granted a declaration that Fingal County Council was in breach of its statutory duty for failing to adopt a Local Area Plan for Malahide, it refused the primary relief of certiorari. The regulations were found to not be invalid as they could be read harmoniously with EU law on standard C-106/89 Marleasing principles.
100 Meter Tall Group v. An Bord Pleanála [2025] IEHC 196
The case concerns the building of a wind turbine out of position from the permitted location (36m from the permitted location). The applicants seized on the consequential modest retention application in order to mount an unsuccessful full-scale challenge to the project. One of the main questions presented to the High Court in this case focused on whether preliminary examination determinations and screening determinations are different concepts within the meaning of Article 4 of the EIA Directive (Directive 2011/92/EC).
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU): The Court did not provide a direct, explicit answer to the above proposed question in its analysis for leave to appeal, as it found that the point did not properly arise on the pleadings and was not of public importance. However, it did note in para. 1 that accepting the applicants’ argument would create a "…disconnect between Irish and EU law" and an "absurd" result. It was also noted in para. 27 that:
- "there is no public interest in the creation of tension between domestic and European legislation by reference to interpreting common terms in different senses; and
- there is no public interest in facilitating unworkable and inconvenient interpretations that defeat the statutory intention that there be a retention.”
- Habitats Directive (Council Directive 92/43/EEC): The applicant also argued that Clare County Council did not have jurisdiction because the application to retain authorised development required an appropriate assessment in accordance with Article 6(3) of the Habitats Directive and Part XAB of the Planning and Development Act 2000 (as amended) (“the 2000 Act”). However, this argument was not pursued in the applicants’ core ground for appeal. The Court implicitly dismissed its relevance in the leave application by focusing on the lack of a substantiated legal challenge and the fact that the applicants' case had effectively dissolved into a single, technical issue concerning the interpretation of s. 34(12)(b) of the 2000 Act.
Key Points in EU Law
Conclusion
The Court found that the applicants lacked evidence of legal precedent to support their claims of error where this issue was litigated within time or indeed at all. The Court determined that this case is not of public importance nor is it likely to help resolve other cases. The Court held that the applicants failed to present any information that could be considered “crucial” to support their claims.
Sweetman v. Environmental Protection Agency and Others [2025] IEHC 144
The applicant sought certiorari quashing the decision of the first respondent to grant an Industrial Emissions License to the notice party for the disposal of animal carcasses and waste. The applicant also sought a declaration that the State had failed to properly transpose Articles 1 to 6 of the EIA Directive into national law regarding the granting of development consent for projects that require such licences.
Relevant EU Directive
- EIA Directive (Directive 2011/92/EU): The Court, however, did not determine the substantive issue regarding the EIA Directive. Holland J. concluded that the applicant lacked the necessary standing to prosecute the proceedings. It was held that the applicant was pursuing an actio popularis, as he professed no personal interest in the environmental effects of the project, lacked proximity to the site, and had not participated in the licence review process. The judgment reaffirmed that while EU law and the Aarhus Convention require “wide access to justice”, they do not mandate that national courts grant standing to any individual to litigate a generalised complaint about the legality of a licensing regime. Consequently, the proceedings were dismissed on this preliminary issue, leaving the core question of the EIA Directive's correct application in this context undecided.
Key Points in EU Law
Holland J. reaffirmed that the "wide access to justice" required by the Aarhus Convention and Article 11 of the EIA Directive does not equate to an actio popularis for any individual. By examining prior national jurisprudence, the Court highlighted the significance of the term “sufficient interest”. The judgment clarifies that while EU environmental law aims for broad access, member states retain the discretion to define "sufficient interest" through national rules, and such rules can permissibly consider factors like a claimant's proximity to a project and their participation in the prior administrative process.
Conclusion
The High Court dismissed the case as the applicant lacked the sufficient legal standing to justify the objection. The issue of whether the Environmental Protection Agency should have conducted an EIA was therefore never decided.
Noel Murphy v. An Bord Pleanála and Fingal County Council [2025] IEHC 117
The applicant sought leave to judicially review the first respondent, An Bord Pleanála’s (“the Board”), decision to grant planning permission for a gas turbine power station in Finglas, Co. Dublin. He challenged the decision on grounds relating to the County Development Plan and alleged failures under the EIA and Habitats Directives. However, he had not participated in any stage of the planning process, despite multiple public consultation opportunities, and admitted he was not personally affected by the development.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU): The applicant argued that the Board failed to comply with its obligations under the EIA Directive, particularly regarding project splitting and the adequacy of the Environmental Impact Assessment (EIA) process. Farrell J. acknowledged in para. 76 that EU law requires “wide access to justice”, but clarified that this does not mean unlimited access, nor does it require standing for any member of the public raising EU law issues:
“EU law allows national courts impose their own rules regarding standing, once the rules are compliant with EU Law – the rules must be applied in a manner which satisfies the “wide access to justice” requirement of the Aarhus Convention.”
Farrell J. recognised that Article 11 (3) of the EIA Directive allows member states to define “sufficient interest” through national rules, as long as these provide for wide access to justice. However, Farrell J. also stressed in para.93 that raising EU law grounds alone does not satisfy the “sufficient interest” test:
“It is appropriate to interpret ‘a sufficient interest’ broadly, but EU law does not require it to be interpreted “as broadly as possible” as the Applicant has submitted” - Habitats Directive (Council Directive 92/43/EEC): The applicant claimed that the Board had failed to properly assess effects on European sites (Malahide Estuary SAC/SPA) under the Appropriate Assessment (AA) obligations in the Directive. Farrell J. accepted that the case raised environmental protection concerns, including issues relating to the Habitats Directive, but ruled that such arguments must be brought by a person with sufficient interest or proximity. Farrell J. observed in para. 103 that the “significance of proximity is linked to potential impact of a proposed development.” There was no evidence that the applicant had any link to or history of engagement with the protected sites, nor any personal connection. He lived 42 kilometres away and had not taken part in the public consultation process.
Key points regarding EU Directives
Farrell J. reiterated that it is Irish law which controls standing, and only where national rules conflict with or fail to meet EU requirements would EU law override them. Farrell J. held that the applicant was not part of the “public concerned” under Article 11 of the EIA Directive because he had not participated in the planning process and had no particular link to the site. Farrell J. rejected the idea that merely invoking EU environmental law grounds, by itself, meets the requirements of “sufficient interest.”
Conclusion
Farrell J. held that the applicant lacked sufficient interest under s. 50A(3)(b)(i) of the Planning and Development Act 2000, citing Grace & Sweetman v. ABP [2017] IESC 10 to emphasise that general concern is insufficient without personal engagement or impact. Leave was refused on the basis that Mr. Murphy did not have standing to bring the claim.
Ryan v. an Bord Pleanála and Others [2025] IEHC 111
This case concerned a judicial review challenge brought by the applicant, against a decision by the first respondent, an Bord Pleanála (“the Board”), to grant planning permission to Analog Devices for the expansion of its industrial campus. The applicant contested the permission on several grounds, primarily arguing that the Board had erred in law by failing to require a full EIA for the project and by not conducting a proper Appropriate Assessment (“AA”) with subsidiary claims related to potential water pollution and a failure to assess cumulative impacts on the environment.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU): The High Court had to determine whether the proposed developments fell within any project classes listed in Annex I or II of the EIA Directive. The Court reiterated that the obligation to conduct an EIA arises only if a project, by its form, nature, or type, is classified under one of the Directive's specified categories. It rejected a broad, purposive interpretation that would bring industrial projects like the Analog Campus under the category of "urban development" as described by Annex II, emphasising that such classifications must be based on the project's inherent characteristics and not merely its location. The Court also clarified that the concept of a "mandatory EIA" in para.160 is better understood as "automatic EIA" for projects exceeding set thresholds, while in para.158-159 "sub-threshold EIA[s]" apply to projects likely to have significant environmental effects, both being mandatory when their respective legal conditions are met.
- The Water Frameworks Directive (Directive 2000/60/EC): While the applicant did not make a specific challenge alleging a breach to the Water Frameworks Directive. Instead, water quality issues were framed within the context of the EIA and AA assessments. The High Court found that the alleged pollution, primarily concerning misconnections to the stormwater system, was not substantiated by evidence linking it to the proposed developments. Consequently, the Board was entitled to rely on the second respondent’s expert evidence and the imposition of a specific planning condition to manage any residual risk of effluent misconnection. The Court emphasised that the primary responsibility for enforcing water quality standards, including those under the WFD, lies with the Environmental Protection Agency (EPA) and other specialised regulatory bodies, not the planning authority within the context of a development consent decision.
Key EU Law Points
The EIA Directive applies only to projects falling within the classes specified in Annex I or II. The High Court examined the principle from the CJEU case Kraaijeveld (C-72/95) which, in para. 31, established that the EIA Directive has a "…wide scope and a broad purpose" to ensure that projects likely to have significant environmental effects are properly assessed. Therefore, the Courts should interpret the categories in Annex II broadly and purposively to ensure the Directive's environmental objectives are not undermined by legal technicalities. National courts may exercise discretion to refuse relief if quashing a decision would serve no substantive environmental purpose, particularly where EIA obligations were not engaged.
The enforcement of Water Framework Directive objectives falls primarily to specialised environmental regulators, not the planning process. A planning permission cannot be invalidated by general accusations of water pollution; any alleged breach of the WFD must be specifically pleaded and supported by evidence demonstrating a causal link to the project. The High Court affirmed the distinct roles of planning and environmental authorities, noting that the EPA holds the statutory duty for monitoring and enforcing discharge compliance.
Conclusion
The High Court dismissed the judicial review. It held that the proposed developments did not fall within any project class under the EIA Directive. Furthermore, the Court found that the AA conducted was lawful and rational, and that the planning authority had adequately addressed all environmental concerns, including those related to water quality, through evidence-based analysis and the imposition of specific planning conditions.
100 Meter Tall Group and Others v. an Bord Pleanála [2025] IEHC 42
This case concerned the building of a wind turbine out of position from the permitted location (36m from the permitted location). The permission was granted by the respondent, an Bord Pleanála (“the Board”). After a preliminary determination found that the modest positional change did not require Environmental Impact Assessment (EIA) screening, the developer obtained retention permission. The applicants challenged this decision, arguing that the very act of conducting a preliminary EIA assessment meant the more onerous ‘substitute consent’ process was required, making the retention permission invalid. The question became whether the respondent had demonstrated any specific illegality which warranted certiorari.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU): The applicants argued that there was an error of law as it was made in breach of Article 4 and/or Annex II, Annex IIA and/or Annex III of the EIA Directive; specifically, that the Clare County Council did not have the jurisdiction to grant the application to retain the unauthorised development because the notice party was required to make an application for substitute consent directly to the respondent with respect to the unauthorised development in accordance with Part XA of the Planning and Development Act 2000 (as amended).The Court rejected the applicants' argument that the planning authority lacked jurisdiction. It held that the grant of retention permission was not precluded in this instance because a key condition for the statutory prohibition was not met. The Court reasoned that the respondent had lawfully conducted a preliminary examination of the sub-threshold development, which concluded that there was no real likelihood of significant environmental effects and thus no need for a full EIA screening determination. Since the version of s. 34(12) of the Planning and Development Act 2000 in force at the time only prohibited retention permission if a "screening determination" was required, and the Board validly ruled one out at the preliminary stage, the prohibition was never triggered.The Court held that the term "screening determination" in domestic law must be interpreted consistently with the EIA Directive, which itself distinguishes between a “preliminary examination” and a “formal screening determination”. By finding that a valid preliminary examination that excludes the need for further assessment does not equate to a "screening determination," the Court aligned the national procedure with EU principles.The applicants also argued that the proposed development constituted project splitting contrary to Article 4 of the EIA Directive. The Court clarified that the doctrine of project-splitting under Article 4 involves an objective assessment of whether a single project has been artificially fragmented to evade EIA obligations, rather than an inquiry into the developer's subjective intent. The Court held that the remedy for unlawful project-splitting is not the invalidation of the permission but rather an obligation on the decision-maker to assess the application in the context of the overall project and its cumulative and in-combination effects. On the facts, the Court found no project-splitting, as the elements in question were either already permitted or were not part of a single project with the development under review.The applicant also argued that the impugned decision was invalid as it breached Article 6(5) of the EIA Directive because the Noise Assessment Reports and Shadow Flicker Reports were not made electronically accessible to the public on the Clare County Council's website. The Court highlighted however that the respondent was not the Clare County Council, hence the argument was not relevant to the current proceedings.
- Habitats Directive (Council Directive 92/43/EEC): The applicant argued that the respondent’s decision was invalid because it contravenes Article 6(3) of the Habitats Directive, claiming that the respondent failed to carry out an appropriate assessment without lacunae, and which failed to contain complete, precise, and definitive findings and conclusions capable of removing all reasonable scientific doubt.
The Court rejected this argument, finding that the applicants had failed to meet the requisite legal and evidentiary standards. The Court held that the plea was inadequately particularised, amounting to a general assertion rather than a properly pleaded ground that identified precisely how the scientific doubt arose. To substantiate such a claim, an applicant must normally provide expert evidence in the proceedings to demonstrate that the material before the decision-maker created a reasonable scientific doubt that was not dispelled, or that the board's scientific approach was flawed. The applicants provided no such expert affidavit, and the Court found that the inspector's report had in fact engaged with the specific issues raised, such as hydrological connectivity and impacts on bird species, providing reasoned conclusions capable of removing doubt. Consequently, the applicants did not fulfil the burden of proof.
Key points in EU Law
The EIA Directive requires environmental assessments to be conducted prior to development consent, and that post-hoc regularisation of unauthorised development is only permissible under exceptional circumstances without circumventing this core obligation as established in Commission v. Ireland (C-50/09). Furthermore, the Habitats Directive was interpreted as requiring that any scientific doubt about a project's impact on European sites must be dispelled before approval, but this obligation does not require the decision-maker to rebut every individual submission; rather, it must provide a reasoned conclusion capable of removing all reasonable scientific doubt, with the burden resting on the applicants to prove any failure with evidence.
Conclusion
The High Court dismissed the challenge and upheld the planning permission. It concluded that the planning board acted lawfully because a valid preliminary examination ruled out the need for a full environmental impact assessment, meaning the legal prohibition on retention permission did not apply. Furthermore, the Court held that the applicants' various grounds of challenge were either inadequately argued or supported by insufficient evidence to prove any specific illegality in the respondent’s decision.
Eco Advocacy CLG v. An Bord Pleanála [2025] IEHC 15
The applicant applied to the High Court seeking an order of certiorari by way of application for judicial review quashing a decision made by the respondent, an Bord Pleanála, to grant planning permission to the notice party, Statkraft Ireland Ltd on appeal for a wind farm development. The applicant also sought a declaration that the decision contravened the public participation requirements of EU law, because it claimed that the Board failed the make the amended Environmental Impact Assessment Report (EIAR) available on its website; an order providing for the costs of the application; and a stay on the decision's operation pending the Court's ruling.
Relevant EU Directives
- Habitats Directive (Council Directive 92/43/EEC): The applicant argues that the respondent failed to comply with Article 6(3) of the Habitats Directive by unlawfully screening out the hen harrier from an AA. The core of this contention is that the Board’s decision was not based on the best scientific knowledge, as it failed to properly engage with and dispel the reasonable scientific doubts raised by the National Parks & Wildlife Service regarding inadequate bird surveys and the risk posed by turbine blades to the birds' flight paths. The legal standard, as emphasised by the applicant with reference to CJEU jurisprudence such as Coöperatie Mobilisation for the Environment (C-293/17) and Sweetman (C-258/11), is that an Appropriate Assessment (“AA”) must contain complete and definitive findings capable of removing all reasonable scientific doubt.
- EIA Directive (Directive 2011/92/EU): The applicant contends that the respondent breached its obligations under the EIA Directive, specifically Articles 6(3)(b) and 9(1), by failing to make a complete and accessible EIAR available to the public. The argument distinguishes between two temporal obligations: the duty under Article 6(3)(b) to make the EIAR available during the appeal process, and the duty under Article 9(1) to publish the decision and relevant documents after the decision has been made. As an environmental NGO, the applicant was held by the High Court to be indirectly prejudiced because the absence of a complete and intelligible EIAR on the Board’s website hindered its ability to enforce the implementation of mitigation measures. The Board’s website did not serve its required function under EIA Directive to make environmental information electronically accessible through a centralised and easy to access portal, thereby undermining the public’s right to participate in environmental decision-making as guaranteed by the Directive.
Key EU Law Points
Conclusion
The High Court concluded that the application for judicial review was largely unsuccessful. While it granted a declaration the respondent had breached its publication duties under the Planning and Development Act 2000 by using incomprehensible file names on its website, it refused the primary order of certiorari to quash the planning permission. The Court held that this publication failure, occurring after the decision was made, did not invalidate the permission, especially as the applicant suffered no specific prejudice. Furthermore, the Court found no infirmity in the AA screening, ruling that the respondent was not obliged to provide a point-by-point rebuttal to submissions and had sufficiently reasoned its decision to screen out the hen harrier, with costs awarded to the applicant only for the issue on which it succeeded.
Nagle View Turbine Aware [No. 2] v. an Bord Pleanála [2025] IEHC 3
This case is an application for leave to appeal in the Court of Appeal, following a dismissal of a judicial review from the High Court. The applicant had challenged a wind farm development approved by the respondent. The applicant challenged whether the respondent had conducted a thorough assessment of the noise impacts of the proposed development in circumstances.
Relevant EU Directives
- EIA Directive (Directive 2011/92/EU): The applicant questioned whether the respondent’s assessment was as “complete as possible” according to the EIA Directive. The applicant’s frame of reference for the Directive was from Solvay v. Région Wallonne (Case C 50-09). The High Court determined that the applicant had not established any unreasonableness in carrying out the EIA. The applicant in judicial review proceedings bears the overall onus of proof.
Key EU Law points
Humphreys J. reiterated that the burden of proof in judicial review proceedings rests on the applicant, who must not merely assert but must evidentially prove any alleged failure in the assessment process. The proposed points of law were found to be based on non-factual premises, incorrectly characterised the judgment, and included unasserted points.
Conclusion
Humphreys J. refused the application for leave to appeal. The High Court found that the applicant’s points of law were not of exceptional public importance, were fact-specific, and did not transcend the circumstances of the case.
Reid v. An Bord Pleanála & Ors [2024] IEHC 27
The applicant, a farmer, challenged planning permission granted to Intel Ireland Ltd by the first respondent, An Bord Pleanála ("the Board"), for modifications to a manufacturing facility in Leixlip, Co. Kildare. The changes involved increased building heights and changes to chemical storage. The applicant's previous challenges in 2017 and 2019 to planning permissions had both failed. Crucially, the applicant argued that the Board broke EU environmental laws by not properly assessing the environmental impact, not following correct planning procedures, and failing to publish its decision online for the public in time. This case focused on whether the 2020 decision complied with obligations under three key EU environmental directives.
Relevant EU Directives
- Habitats Directive (Council Directive 92/43/EEC): In line with Article 6(3) of the Habitats Directive, Humphreys J. noted that a competent authority must provide reasons to show that there is no reasonable scientific doubt as to a project’s effects on a protected site as established in Eco Advocacy (C-721/21) (para. 65). Mr. Reid claimed that the board failed to properly assess ecological risks. Humphreys J. found that the Appropriate Assessment (AA) screening was included in the inspector’s report, which the board lawfully adopted. While clearer documentation was encouraged, Humphreys J. held in para. 71 that “implicit adoption by the board of the inspector’s report on such matters is not in itself a basis to quash a decision.”
- EIA Directive (Council Directive 2011/92/EU): Mr. Reid alleged that the Intel development should have undergone EIA screening. Humphreys J. rejected this, finding that the Intel development did not fall within Annexes I or II of the Directive. Therefore, no screening or full EIA was legally required. Humphreys J. concluded in para. 86 that it was clear “that this is not an EIA project for the simple reason that it does not come within Annexes I and II of the EIA directive.”
- Seveso III Directive (Council Directive 2012/18/EU): Under this directive, industrial sites storing hazardous substances must assess environmental risk. The applicant cited Intel’s storage of silane, and whilst Humphreys J. acknowledged this, he held that the facility was not primarily used for chemical storage and thus, did not qualify under the relevant Annex II categories as the Directive applies only to dedicated chemical storage facilities. Humphreys J. agreed with the Board, stating in para. 79 that: “Put simply, a facility which manufactures circuits and circuit boards is not an industrial estate development project nor is it a facility for the storage of chemicals.”
Key EU Law Points
Regarding remedial obligations, Humphreys J. rejected the applicant’s claim that a fresh AA was required due to earlier alleged defects, noting no prior legal finding of invalidity, no formal request for a remedial AA, and that the EPA had addressed the relevant concerns. Humphreys J. held in para. 62 that “…the applicant hasn’t come anywhere near even attempting [to prove a prior AA breach].” As outlined in para.139, although the substantive planning challenge failed, the Court issued a declaration under the Aarhus Convention, finding that the Board breached its duty by failing to publish its decision online for over 18 months: “This is not a minor or insignificant matter and warrants being marked appropriately by a declaratory order”.
Conclusion
Humphreys J. upheld the planning permission granted to Intel in 2020. However, Humphreys J. issued a declaration against the Board for breaching public access obligations by failing to publish the decision in a timely manner.